Zesa tariff increase imminent

10 Jan, 2016 - 00:01 0 Views
Zesa tariff increase imminent Zesa loses millions of dollars due to its flawed distribution system

The Sunday Mail

Tinashe Farawo
GOVERNMENT could soon approve the increase of electricity tariffs by at least 22 percent in an effort to finance new power generation projects and ensure a steady power supply.
Although consultations are still underway, the Zimbabwe Energy Regulatory Authority is expected to approve a tariff increase requested by the Zimbabwe Electricity Supply Authority.
This will see electricity charges rise from the current average of USc9 per kilowatt hour to USc12/kWh.
Energy and Power Development Minister Dr Samuel Undenge told The Sunday Mail that the increase was imminent although consultations with consumers were still ongoing.
Dr Undenge said to fill the gap created by the drastic fall of water levels in Kariba, there was need for the tariff increase to finance projects that are already underway.
Dr Undenge said energy economics dictated there be a sustainable tariff increase.
“As Government we are conscious of the need to have a moderate increase so as to caution consumers. Zera is going to bring the recommendations, but as Cabinet we are only going to approve what is reasonable,” he said.
“Our current tariffs have not been cost reflective. I am sure we will all agree that our consumers have not been paying and if US$1 billion which is owed Zesa was paid then there was no need for us to get a loan from China to expand the Hwange unit seven and eight.”
Dr Undenge said the last tariff increase came five years ago.
“Most of our neighbours have been increasing power tariffs by 10 percent yearly so this increase is important so that we can be able to finance new projects and the retooling exercise at our thermal stations,” he said.
Retooling of Bulawayo Thermal Station is expected to start in the first half of 2016 and upon completion, at least 70MW will be added to the national grid.
Refurbishment of Harare and Munyati thermal power stations is also expected to start in that period, adding a combined 150MW to the grid.
“We have people who have already won the tenders for the two projects (Harare and Munyati) and this is going to improve our power situation considering the dire situation in Kariba,” Dr Undenge said.
A tender was also awarded to Helcraw Electrical for the Mutare Peaking Plant, which is expected to add 120MW in the short-term.
The emergency Seke Diesel Plant, the minister said, would add about 200MW in the next eight to 12 weeks.
“The Seke project and the Mutare are emergency projects and by early March, we will be having power from there,” he said.
Zimbabwe expects to be electricity self-sufficient in the next five years on completion of various projects, churning out more than 4 000MW by 2020.

Share This:

Survey


We value your opinion! Take a moment to complete our survey

This will close in 20 seconds